Do you understand the acceptance procedure of Hunan elevator project?

Release time: 2022-04-27 08:56:10

News source: Hunan Alpha Elevator Engineering Co., LTD

Elevator installation branch project completion acceptance reference procedure

1. During the completion acceptance, all parties involved in the construction (including the project leader and professional personnel in charge of the construction unit, the director of the supervision unit and the elevator supervision engineer, the project manager of the construction unit and the relevant personnel of the quality department) shall be present。

2. The team leader of the acceptance team (the construction party is the team leader) presides over the completion acceptance。

3. The leader of the acceptance group introduces the personnel of the acceptance group。

4, the construction unit to introduce the project overview and completion。

Hunan elevator project

5, the construction and supervision units shall report respectively the performance of the elevator installation branch project contract and the implementation of laws, regulations and mandatory standards in all aspects of the project construction。

6, the acceptance team personnel respectively check the elevator installation branch project completion data and project physical quality。

7, the acceptance team personnel respectively report the inspection situation and form the preliminary acceptance opinions of the elevator installation branch project。

8, listen to the quality supervision body on the entire elevator installation branch project preliminary acceptance opinions and make corresponding adjustments, the formation of a formal elevator installation branch project completion acceptance opinions (when the construction parties do not agree, should negotiate to put forward solutions。After consensus, re-organize the elevator installation branch project completion acceptance)。

9. The leader of the acceptance team announces the completion acceptance meeting is over。

10. Summarize the archival information of the elevator installation project and enter the archival procedure。